Dhahran Project

The project involves installing 115kV underground cables to connect the 380kV DHO BSP with three substations: DSHO SS#1A, SS#1B, and SS#2, under Contract No. 4400019298.

Project

Installation of 115 kV Underground Cables for the Integration of Dhahran Home Ownership Substations (Contract No. 4400019298)

This project involves the installation of 115 kV underground cables to connect the 380 kV DHO BSP to three 115 kV substations: DSHO SS#1A, DSHO SS#1B, and DSHO SS#2. The objective is to achieve seamless integration of the substations, enhancing grid stability and improving power distribution across the Dhahran Home Ownership area.

Key Components

  • 115 kV XLPE underground power cables
  • Insulated joints
  • Terminations suitable for 115 kV substations
  • All required accessories for complete integration

Scope & Objective

  • Connection of DHO BSP (380 kV) to three 115 kV substations
  • Enhancement of grid stability
  • Improvement of power distribution in the Dhahran Home Ownership area

Project Summary

The project involves installing 115kV underground cables to connect the 380kV DHO BSP with three substations: DSHO SS#1A, SS#1B, and SS#2, under Contract No. 4400019298.