This project involves constructing two 380kV underground cable circuits—6.86 km (ARFTW–MHR) and 13.63 km (ARFTW–SAZ) with XLPE cables, fiber optics, DTS systems, and related civil works. It is being executed under Contract CN-4400019200 and is currently 63% complete.
Project Summary
Project Title: 380 kV Power Cables Between the Arftwa MHR (CKT1) and the Arftwa SAZ (Arftw SAZ) Water Intake Station
Contract Number: CN 4400019200
Signing Date: October 16, 2023
Completion Rate: 63%
Scope of Work
The project includes the installation of 380 kV wire cables between Arftwa MHR (Arftw) and the water metering station. The following main contractors were involved:
380 kV Wire Cable Circuit
Length: 6.86 km (15 sections)
Scope: Installation of a single 380 kV network cable
Components:
Ultraviolet (1x1C) XLPE copper cable, 2500 mm² per circuit
Number of fiber optic connections
Distributed Temperature Sensing (DTS) system
All required accessories
ARFTW SAZ Cables for Underground Electrical Circuits
Length: 13.63 km (30 sections)
Scope: Installation of a single 380 kV underground electrical cable network
Components:
2500 mm² XLPE ultra-clear copper cable per circuit (1x1C)
Number of fiber optic connections
DTS system
All required accessories
Additional Works
Road inspection, soil testing, and analysis
Construction of concrete-sheathed cable trenches and drainage channels
Gravity excavation or technical excavation if underground installation is required
Project Summary
This project involves constructing two 380kV underground cable circuits—6.86 km (ARFTW–MHR) and 13.63 km (ARFTW–SAZ) with XLPE cables, fiber optics, DTS systems, and related civil works. It is being executed under Contract CN-4400019200 and is currently 63% complete.