Civil and Electrical Projects Contracting (CEPCO) has completed specialized HVDC underground cable field testing on three cable circuits in Abu Dhabi, UAE. The company describes it as the first post-installation HVDC cable field testing of its kind in the Middle East.

🔹 Case 1 (20 May 2026): Two new 525 kV HVDC circuits supplied by Sumitomo Electric, each about 140 km long with a Dedicated Metallic Return (DMR) cable. They were tested at -580 kV DC for one hour, followed by a 48-hour discharge.

🔹 Case 2 (6 August 2026): A new Prysmian circuit was integrated with an existing in-service HVDC system, forming a looped length of about 264 km. It was tested at -464 kV DC for one hour, followed by a 48-hour discharge. The lower voltage protected the existing cable.

🔹 Equipment: Testing equipment rated at 800 kV DC / 35 kVA.

HVDC insulation behaves very differently from HVAC under sustained DC stress. Space-charge accumulation, conductivity variations and temperature gradients all have to be managed, so the charging and discharging procedures must be tightly controlled.

The result marks a significant step for specialized high-voltage testing capability in the Gulf region.